On Wednesday, December 19th we will be performing some maintenance on our UPS system. While this maintenance is being performed we will put the UPS system and grid power in bypass and operate the datacenter on generator power. This is standard procedure for work such as this. While we do not expect any change in power delivery, any time power is switched from one source to another, a risk of interruption is possible. Every effort and precaution will be taken to minimize this risk.
We will also be turning up an additional 100kVA PDU in Datacenter 2 to facilitate growth in that area.
Thank You,
--Chuck Goolsbee
VP, Technical Operations
digital.forest, Inc.
posted by Chuck G. at 08:51 AM on Monday, December 17, 2007
Categories: Datacenter Expansion,
Scheduled Maintenance