Between the hours of 9am and 12pm, Thursday, September 20th we will be performing maintenance on our UPS system, which will include upgrading some control boards and updating to the latest firmware. This is the final step in our recent UPS upgrade.
While this maintenance is being performed we will put the UPS system and grid power in bypass and operate the datacenter on generator power. This is standard procedure for work such as this.
While we do not expect any change in power delivery, any time power is switched from one source to another, a risk of interruption is possible. Every effort and precaution will be taken to minimize this risk.
Thank You,
--Chuck Goolsbee
VP, Technical Operations
digital.forest, Inc.
posted by Chuck G. at 10:52 AM on Thursday, September 13, 2007
Categories: Datacenter Expansion,
Facility Maintenance,
Scheduled Maintenance