Move Update: Hosting Servers Move Schedule.
The following servers will be moved on Monday night, Feb 7, starting around 11 pm.
skil
jig-old
power
chain
circular
iron
sabre
buzz
radial
jig
Expected downtime for any server move should be around two hours. We will do everything we can to minimize this as much as possible. All servers listed should be back online by 1 AM.
This will be our first large scale server move, so downtimes will only get shorter, and number of servers moved should increase as the nights go by.
The next servers scheduled to move are:
boysenberry
sage
date
crabapple
woodpecker
tangerine
souari
butternut
These will move on Tuesday, Feb 8, either starting around 2 AM, or 11 PM. Specifics will be posted here as the time approaches.
PLEASE NOTE: As all these devices are rack-mount servers in very tight quarters with each other, we can not specifically call out exact shut-down times. Additionally we may elect to NOT move some particular servers due to space or time constraints. Details will be posted here with specifics at the time of move.
Thanks for your patience.
posted by Chuck G. at 12:25 PM on Sunday, February 6, 2005
Categories: Hosting Servers,
Intergate.West Move